Asphalt plan 2024

From October 28 begins milling and asphalting works in streets Luz Casanova, Profesor Albareda and Fontiveros.

Update:


- Due to the weather, asphalting works in Luz Casanova St will take place in November 4.


Due date for traffic cuts for milling, asphalting and horizontal signs painting works will be according to the following plan:

STREETMILLINGASPHALTINGHORIZONTAL SING PAINTING
STREET LUZ CASANOVA1 DÍA
on 28/10/24 at daytime hours
1 DAY
on 29/10/24 at daytime hours
1DAY
on 30/10/24 at daytime hours
STREET FONTIVEROS
SECTION 1
(between Cno. de la Zubia and Pza. Fontiveros)
10/11/24
(Sunday, from 15:00 to 23:00 h.)
from 23:00 h. of 10/11/24 at 07:00 h. from 11/11/24
(night from Sunday to Monday)
12/11/24
(Tuesday at daytime hours from 10:00 to 18:00)
STREET FONTIVEROS
SECTION 2
(between Pza. Fontiveros and C/Bruselas)
from 23:00 h. on 10/11/24 to 07:00 h. on 11/11/24
(night from Sunday to Monday)
from 23:00 h. on 11/11/24 to 07:00 h. on 12/11/24
(night from Monday to Tuesday)
13/11/24
(Wednesday at daytime hours from 10:00 to 18:00)
STREET PROFESOR ALBAREDA
(in/ roundabout Cno.Bajo Huetor)
from 23:00 h. on 11/11/24 to 07:00 h. on 12/11/24 (night from Monday to Tuesday)at 23:00 h. on 12/11/24 to 07:00 h. on 13/11/24 (night from Tuesday to Wednesday)14/11/24
(Thursday at daytime hours from 10:00 to 18:00)

Suppresion of parking area will be carried out at 00:00 hours of previous day to avoid transfer of vehicles at the beginning of each working day.

Schedule might have changes due to the weather, machine failure, lower yields than expected, etc that should be coordinated with this Technical Office and Local Police as soon as possible.