Traffic cuts in Tendillas de Santa Paula St take place from May 1st 2024 to 31 December 2025.
Traffic cuts in Tendillas de Santa Paula St to carry out loading and unloading works will be from May 1st 2024 to December 31 2025 as follows:
* Demolition phase: during four months there will be dayly intermittent traffic cuts to remove containers between 9:30 and 13:30 hours or between 15:30 to 18:30 hours, just the time needed to carry out these works.
* Foundation and structure phase: during the rest of works, will be carried out puctual traffic cuts in off peak hours, in non consecutive weeks to supply material, maximum of 30 minutes, on Tuesday, Wednesday or Thursday, between 9:30 and 13:30 hours or between 15:30 hours to 18:30 hours
* Conreting works: will be six times, carrying out three hours duration traffic cuts between 9:30 and 13:30 or between 15:30 and 20:30 hours, on Tuesdays, Wednesdays or Thursdays.
The street can not be closed to traffic when works are not being carrying out. There must be free access to garages in the area when works allow it.
File 9.109/24