Due date for traffic cuts in Moral de la Magdalena 33 (between Solarillo de Gracia and San Miguel Alta streets) will be one year since May 1st 2024.
* Land movement phase: during one month will be carried out intermittent traffic cuts between 9:30 and 13:30 hours or between 15:30 hours to 18:30 hours for three working days in non-consecutive weeks aproximately four hours duration on Tuesday, Wednesday or Thursday.
* Foundation phase and Retaining Walls: during three months will be carried out punctual traffic cuts in off peak hours, two working days in non-consecutive weeks to supply goods 3 or 4 hours duration, on Tuesday, Wednesday or Thursday.
* Enclosure phase and rest of works: will be eight months from the end of previous phase, making occasional cuts one hour duration each, between 9:30 and 13:30 hours or between 15:30 and 18:30 hours. Entrance and exit hours of schools should be avoided. The street can not be shut to traffic when works are not being carried out.
File 8.343/24