Total traffic cut in Moral Alta nº7 will be from 25/01/21 for eighteen months following this plan:
Demolition works: It would be done in five days, from 8:00 to 18:00 hours.
Concreting works: Five times four hour duration each, from 9:30 to 13:30 hours, or from 15:30 hours. It will not be possible to cut traffic in Santiago Street.
Structuring works : will last four months making intermittent traffic cuts three hours duration each, from 9:30 to 13:30 hours, and from 15:30 hours.
Rest of works: will last fourteen months, making intermittent traffic cuts one duration each, from 9:30 to 13:30 hours, and from 15:30 hours.
There must be free access to garages of the area at any moment.