Total traffic cut in Verónica de la Virgen
Total traffic cut in Verónica de la Virgen (section between San Antón and San Isidro streets) for 4 months from 5 June 2020.
Road works will be done according to this plan:
- Surfacing phase: For one month. It will be 3 times/week for three hours each, between 7:00 and 10:00 and from 15:30 to 18:30 hours, from Monday to Thursday and free access to private parking.
- Structuring phase: For three 3 months. It will be two times/week for three hours each, between 7:00 to 10:00 and from 15:30 to 18:30 hours, from Monday to Thursday and free access to private parking.