In november of 2013 there will be several Works along the differents districts of the city in the Asphalt Plan.
Between the 18th and the 25th of november there will be developed several asphalt Works in the streets of the city of Granada.
These are the expected dates of the traffic.
North District
- 18/11/2013 - Casería de Aguirre: Section between Joaquina Eguaras st and Pedro Machuca st
5803.25 m2
- 19/11/2013 - Gobernador Pedro Temboury: Section between Joaquina Eguaras st and Juan Pablo II avenue
4686 m2
Beiro District
- 20/11/2013 - Roundabout of Juan Pablo II avenue crossing with Tete Montoliu st
2500 m2
Chana District
- 20/11/2013 - Periodista Fernando Gómez de la Cruz: ascent side of the Europa Roundabout
550 m2
- 20/11/2013 - Brocal
256 m2
- 21/11/2013 - Trucha
626.73 m2
City Center District
- 21/11/2013 - Almona de San Juan de Dios
646 m2
Genil District
- 22/11/2013 - Paseo Hermanos Costaleros
540.37 m2
Distrito Zaidín
- 22/11/2013 - Compositor Luis Megías
450 m2
- 25/11/2013 - Fuerteventura
413.81 m2
- 25/11/2013 - Placeta Fernando de Rojas
581.79 m2
- 25/11/2013 - Placeta Juan de Mena
200 m2
Total are 17.253 m2.
Check the maps with the situation of the different paving works.